Excel for Project Management: Gantt Charts, Trackers, and Timelines
Build project management tools in Excel. Create Gantt charts, milestone trackers, resource allocation views, and project dashboards without specialized PM software.
Dedicated PM tools are great, but sometimes you need the flexibility of Excel — for quick projects, custom views, or when stakeholders prefer spreadsheets over yet another app login.
Project Task List Structure
Essential columns for task tracking:
- Task ID and name
- Start date and end date
- Duration (calculated or manual)
- Owner/assignee
- Status (Not Started, In Progress, Complete, Blocked)
- % Complete
- Dependencies (which tasks must finish first)
Building a Gantt Chart
Create a Gantt chart using conditional formatting:
- Create date headers across the top (one column per day/week)
- Use conditional formatting formula: =AND(H$1>=$C2, H$1<=$D2)
- Apply a fill color when the formula is true
- Result: bars appear for each task's duration
Add a second condition with different color for completed portions.
Duration and Date Calculations
Working days duration: =NETWORKDAYS(StartDate, EndDate)
End date from duration: =WORKDAY(StartDate, Duration)
Days remaining: =MAX(0, EndDate-TODAY())
Days overdue: =IF(AND(Status<>“Complete”, EndDate<TODAY()), TODAY()-EndDate, 0)
Milestone Tracking
Flag milestones separately from regular tasks:
- Add a “Type” column (Task vs. Milestone)
- Milestones have duration = 0
- Use different Gantt formatting (diamond shape or different color)
- Create a milestone summary view with FILTER or QUERY
Resource Allocation View
Track who's working on what:
=SUMPRODUCT((Owner=“John”)*(StartDate<=WeekEnd)*(EndDate>=WeekStart))
This counts tasks assigned to John that overlap with the given week. Create a matrix with team members as rows and weeks as columns.
Project Dashboard Metrics
- % Complete: =AVERAGE(PercentComplete) or SUMPRODUCT for weighted
- Tasks on track: =COUNTIFS(Status,“<>Complete”,EndDate,“>=”&TODAY())
- Tasks at risk: =COUNTIFS(Status,“<>Complete”,EndDate,“<”&TODAY())
- Days to deadline: =ProjectEndDate-TODAY()
Enter Dates Faster with a Real Date Picker
Excel doesn't have a built-in date picker. XLNavigator adds a calendar popup that makes date entry fast and error-free.
Related Reading
- Time Tracking — schedule around weekends
- Date Validation — ensure valid project dates
- Conditional Formatting — visual task status
Official Resources
- WORKDAY function — calculate working days
- NETWORKDAYS function — count working days