Excel for Project Management: Gantt Charts, Trackers, and Timelines

Build project management tools in Excel. Create Gantt charts, milestone trackers, resource allocation views, and project dashboards without specialized PM software.

Excel Gantt chart for project management

Dedicated PM tools are great, but sometimes you need the flexibility of Excel — for quick projects, custom views, or when stakeholders prefer spreadsheets over yet another app login.

Project Task List Structure

Essential columns for task tracking:

  • Task ID and name
  • Start date and end date
  • Duration (calculated or manual)
  • Owner/assignee
  • Status (Not Started, In Progress, Complete, Blocked)
  • % Complete
  • Dependencies (which tasks must finish first)

Building a Gantt Chart

Create a Gantt chart using conditional formatting:

  1. Create date headers across the top (one column per day/week)
  2. Use conditional formatting formula: =AND(H$1>=$C2, H$1<=$D2)
  3. Apply a fill color when the formula is true
  4. Result: bars appear for each task's duration

Add a second condition with different color for completed portions.

Duration and Date Calculations

Working days duration: =NETWORKDAYS(StartDate, EndDate)

End date from duration: =WORKDAY(StartDate, Duration)

Days remaining: =MAX(0, EndDate-TODAY())

Days overdue: =IF(AND(Status<>“Complete”, EndDate<TODAY()), TODAY()-EndDate, 0)

Milestone Tracking

Flag milestones separately from regular tasks:

  • Add a “Type” column (Task vs. Milestone)
  • Milestones have duration = 0
  • Use different Gantt formatting (diamond shape or different color)
  • Create a milestone summary view with FILTER or QUERY

Resource Allocation View

Track who's working on what:

=SUMPRODUCT((Owner=“John”)*(StartDate<=WeekEnd)*(EndDate>=WeekStart))

This counts tasks assigned to John that overlap with the given week. Create a matrix with team members as rows and weeks as columns.

Project Dashboard Metrics

  • % Complete: =AVERAGE(PercentComplete) or SUMPRODUCT for weighted
  • Tasks on track: =COUNTIFS(Status,“<>Complete”,EndDate,“>=”&TODAY())
  • Tasks at risk: =COUNTIFS(Status,“<>Complete”,EndDate,“<”&TODAY())
  • Days to deadline: =ProjectEndDate-TODAY()

Enter Dates Faster with a Real Date Picker

Excel doesn't have a built-in date picker. XLNavigator adds a calendar popup that makes date entry fast and error-free.

Try Date Picker Free

Related Reading

Official Resources

📧

Want more Excel tips like this?

Get our free guide: 10 Excel Shortcuts Microsoft Doesn't Tell You About
Join 3,000+ Excel users boosting their productivity.

By subscribing, you agree to receive the free guide and occasional emails with Excel tips and product updates. Unsubscribe anytime. We respect your privacy.